Ashton Creek Project

Description of the Project

This Project involves the installation of two 500 kilovolt (kV), 250 megavolt-ampere reactive (MVAR) switched shunt capacitor banks at the Ashton Creek Substation to support generation expansion in the Columbia River system, including the addition of Revelstoke Unit 5 and maintain the reliability of the system in the region. These will be the first 500 kV switched shunt capacitor banks installed on the BC transmission system.

The new equipment to be added will require an expansion of the existing substation fence. It is expected that the expanded area will be contained within the property owned by BC Hydro for the existing substation and that no additional land will be required.

This project was included in the Capital Plan and has been approved by the BC Utilities Commission.

Schedule

Milestone Date (subject to change)
Project start-up May 2008
Environmental Management Plan complete April 2009
Contract for turnkey supply & install contract award March 2009
On-site construction start   Summer 2009
Target In-Service date August 2010
Project completed November 2010

 

Project Status Reports

As at:  June 30, 2010

  • The project is proceeding on schedule
  • Contract for turnkey supply & install contract has been awarded to ABB
  • Major equipment is now installed
  • Protection and Control work is on schedule
  • Testing and commissioning has commenced