BC hydro: Transmission
Go to bchydro.com
Search:
Projects
Overview
Events
Seymour Arm Series Capacitor (SASC) Station Project
Transmission System
Overview
Actual Flow Data
ATC Methodology
Balancing Authority Load Data
Engineering Studies & Data
Maps
Reliability
System Operating Orders
System Outages
Transmission Planning
Regulatory Filings
Overview
Capital Plan
Capital Projects
Revenue Requirements
Tariff
Other Filings
Generator Interconnection
Overview
Load Interconnections
Requirements
Standard Generator Interconnection Procedures
BC Hydro’s Calls for Power: Interconnection Procedures
Queue
Engineering Studies & Data
Workshops & Presentations
FAQ
Contact Us
Transmission Scheduling
Overview
Agreements
Bulletins
Business Practices
Customer Service
OASIS
Study Metrics
Tariff & Pricing
Transaction Data
Transmission Services
Workshops & Presentations
Home
>
Projects
> Project Schedule
Project Schedule
Key Milestones
Milestone
Date (subject to change)
Mobilize to site and install safety fencing
mid-September 2008
Prepare for delivery and installation of new transformer, including:
-removal of grass and soil
-removal of concrete planters, seating areas and stairs
late September to mid January 2009
Deliver and install new transformer
January 31 and February 1 2009
Site restoration
February through September 2009
Park re-opening
September/October 2009
In this section:
Description of Project
Project News
Projects
Overview
Events
Seymour Arm Series Capacitor (SASC) Station Project
Copyright 2012 © BC Hydro. All Rights Reserved.
Go to bchydro.com
Login
Subscription
Legal
Privacy Statement
Site Index