Home > Projects > Project Schedule

Project Schedule

Key Milestones

Milestone

Date (subject to change)
Mobilize to site and install safety fencing mid-September 2008
Prepare for delivery and installation of new transformer, including:
-removal of grass and soil
-removal of concrete planters, seating areas and stairs

late September to mid January 2009

Deliver and install new transformer January 31 and February 1 2009
Site restoration February through September 2009
Park re-opening September/October 2009