Home > Regulatory Filings > Capital Projects > Current Capital Projects > Interior to Lower Mainland Transmission Project (ILM) Environmental Assessment (EA) Application

Interior to Lower Mainland Transmission Project (ILM) Environmental Assessment (EA) Application

BCTC submitted a Project Description for the ILM – Nicola to Meridian transmission line option (PDF, 622 KB) with the Environmental Assessment Office on 4 December 2006.

BCTC submitted an Updated ILM Project Description Revision 2 (PDF, 845 KB) on 13 March 2007.

BCTC submitted an Updated ILM Project Description Revision 3 (PDF, 540 KB) on 17 September 2007.

The Environmental Assessment Office approved the Application Terms of Reference (PDF, 528 KB) for the ILM Project on 23 May 2008.

BCTC filed its application on 13 November 2008 for an Environmental Assessment Certificate to the BC Environmental Assessment Office on the Interior to Lower Mainland Transmission Project.

 

On 9 June 2009 the BC Environmental Assessment Office issued an Environmental Assessment Certificate (PDF, 5.2 MB).